Forest Clearance has been accorded by MoEF & CC on 05-01-2021 with conditions to deposit an amount of Rs. 7116.60 lakh against CAT Plan & balance amount of Rs. 1735.50 lakh against NPV & CA for forest land transfer.
As per guidelines of MoEF, For drinking water project environment clearance is not required and all compliances of SEIAA will be completed during tendering process.
| S. No. | Obtained Clearances | According Agency | Accordance Date |
|---|---|---|---|
| 1. | Hydrology | C.W.C. | 22-04-2019 |
| 2. | Interstate clearance | C.W.C. | 06-01-2020 |
| 3. | International clearance | C.W.C. | 19-12-2019 |
| 4. | Geology Report | G.S.I. | Report Available |
| 5. | Dam Design | C.W.C. | 31-10-2019 |
| 6. | Water Conveyance System design | I.I.T Roorkee | Report Available |
| 7. | FE & SA (Foundation Engineering & Seismic Aspects) | C.W.C. | 26-02-2020 |
| 8. | National Board of Wild Life (NBWL) | MoEF & CC | 24-09-2021 |
| 9. | Forest Stage-I Clearance | MoEF & CC | 05-01-2021 |
| 10. | Environment Clearance Quarry 1 | SEIAA | 29-07-21 |
| 11. | Environment Clearance Quarry 2 | SEIAA | 29-07-21 |
| 12. | Environment Clearance Quarry 3 | SEIAA | 29-07-21 |
| 13. | Environment Clearance | SEIAA | 03-01-2024 |
| 14. | Environment Clearance MoEF | MoEF & CC | 05-03-24 |
| 15. | Forest Stage-II Clearance | MoEF & CC | 28-10-24 |
| 16. | Issuance of NOC for Song Dam | Ministry of Tribal Affairs | 20-11-24 |
| 17. | Prior permission for Construction of Song Dam | NMCG | 07-10-24 |