Sanctions/Clearances

Final Clearances to be Obtained

Forest Clearance has been accorded by MoEF & CC on 05-01-2021 with conditions to deposit an amount of Rs. 7116.60 lakh against CAT Plan & balance amount of Rs. 1735.50 lakh against NPV & CA for forest land transfer.

As per guidelines of MoEF, For drinking water project environment clearance is not required and all compliances of SEIAA will be completed during tendering process.

Clearances Obtained
S. No. Obtained Clearances According Agency Accordance Date
1. Hydrology C.W.C. 22-04-2019
2. Interstate clearance C.W.C. 06-01-2020
3. International clearance C.W.C. 19-12-2019
4. Geology Report G.S.I. Report Available
5. Dam Design C.W.C. 31-10-2019
6. Water Conveyance System design I.I.T Roorkee Report Available
7. FE & SA (Foundation Engineering & Seismic Aspects) C.W.C. 26-02-2020
8. National Board of Wild Life (NBWL) MoEF & CC 24-09-2021
9. Forest Stage-I Clearance MoEF & CC 05-01-2021
10. Environment Clearance Quarry 1 SEIAA 29-07-21
11. Environment Clearance Quarry 2 SEIAA 29-07-21
12. Environment Clearance Quarry 3 SEIAA 29-07-21
13. Environment Clearance SEIAA 03-01-2024
14. Environment Clearance MoEF MoEF & CC 05-03-24
15. Forest Stage-II Clearance MoEF & CC 28-10-24
16. Issuance of NOC for Song Dam Ministry of Tribal Affairs 20-11-24
17. Prior permission for Construction of Song Dam NMCG 07-10-24